Orica Timaru Terminal Upgrade
- Company: Orica Chemnet
- Location: Timaru, New Zealand
- Date: July 2008 - July 2009
Overview & Outcome
In this project, CMS supplied project management to oversee all mechanical, electrical & civil work.
The project also involved the following:
- Installation of hypo plant
- Fabrication & installation of pipework and ultrasolv tanks
- Tanker Filling Gantry Fall Protection
CMS Project Supervisor
Rob Wakefield
Project Manager
Phil Muster - Orica Chemnet
Listing Lead In Text: